Knowledge · Service & Operation
Service & Operation
Keeping the line running after commissioning: the start-up sequence that protects the screw, the fault tree we use on the phone, maintenance intervals from 250 to 10,000 hours, and what actually moves your kWh per kilogram.
- Twin Screw Extruder Startup: The 9-Step Sequence That Protects the Screw
Most screw damage happens in the first ten minutes of a shift, not in the tenth month of service. Here is the sequence we teach at commissioning, with the temperatures and checks that matter.
Service & operation · 7 min read - Twin Screw Extruder Troubleshooting: Nine Symptoms, Nine Causes
Most faults reported as 'the machine is not working' resolve to feeding, vacuum, temperature or wear. This is the tree we use on the phone before anyone books a flight.
Service & operation · 9 min read - Extruder Maintenance Schedule: 250 / 2,500 / 5,000 / 10,000 Hours
What to check at each interval, and the three measurements that tell you a wear part is finished before it fails.
Service & operation · 6 min read - Extruder Energy Consumption: kWh per kg, and Where It Goes
Specific energy for compounding typically lands between 0.12 and 0.35 kWh/kg. This article shows which of the two ends you are on, and what actually moves the number.
Service & operation · 5 min read
FAQ
My machine shows a fault not covered in the troubleshooting tree.
Send the symptom, the material, the screw configuration and the last maintenance date. Photographs of the wear parts help more than photographs of the control panel. We answer most diagnostic enquiries the same week.
Do you provide on-site service outside China?
Yes — commissioning, FAT supervision and breakdown support. For wear parts, the maintenance schedule page lists what to keep on the shelf so a two-week lead time never stops the line.